Mrs. Dorothy Lowe Carr Obituary | 0x56ff3d9d | Ms. Margaret Tyner Obituary | Mr. Isaac Rowe Obituary | Donald Duwayne Bullard Obituary | Donald Duwayne Bullard Obituary | Donald Duwayne Bullard Obituary | 0x56ff3d9d | 



On Monday, the Chambers County Commission approved multiple road and bridge projects from the 2025 County Rebuild Alabama Transportation Plan.




Those projects are as follows:

Resurface and Traffic Stripe CR 114 from SR 77 East for 4.22 miles to US. 431 

Resurface and Stripe CR 83 from CR 177 north for 3.52 miles to Cusseta

Reconstruct, Chip Seal, and Traffic stripe CR 288 from CR 278 north for 1.58 miles to the Georgia state line

Reconstruct, Chip Seal, and Traffic Stripe CR 263 from CR 267 East for 3.12 miles to CR 266

Reconstruct, Chip Seal, and Traffic Stripe CR 258 from US 431 North for 4.6 miles to CR 234

Widen, Resurface, and Traffic Stripe County Road 281 from 278 North for 1.02 miles to Randolph County 

Install Seal Treatment and Traffic Stripe CR 289 from N.18th Street North for 5.78 miles to CR 216

Install Seal Treatment and Traffic Stripe CR 388 from Lee CR 266 East for 4.11 miles to US Hwy 29

Replace bridge 90 on CR 02 over Little Sandy Creek

Replace bridge 103 on CR 46 over County Line Creek 

Replace bridge 148 on CR 156 over Chikasanoxee Creek

 
Afterward, Harvill updated the Commission on various road projects going on now and some that will begin in September.


For the complete Chambers County Rebuild Alabama 10-year Transportation plan click on the link below. 

https://drive.google.com/drive/folders/1HjHGqIgVv2BmDX9ZEqYAbTkK8zXJhoUI 

Leave a Reply